INDOT Releases Falsework Removal Construction Memo

INDOT has released a USP to implement the falsework specification revisions that the ICI/INDOT Joint Cooperative Bridge Subcommittee worked on this spring.

BACKGROUND

Back in the fall of 2015, several contractors notified ICI that multiple INDOT district personnel had enforced a full 15-day period before any bridge falsework could be removed. The common practice is that falsework could be removed after achieving a desired flexible strength, typically after two to five days post pour.

SPECIFICATION REVISION HIGHLIGHTS

  • For falsework under a slab top: falsework shall remain in place at least seven days and attain or exceed a 480 psi flexural strength.
  • For falsework under a bridge deck including overhang: falsework shall remain in place at least three days and attain or exceed a 480 psi flexural strength.
  • For substructure falsework: falsework shall remain in place at least three days and attain or exceed a 480 psi flexural strength

Per the INDOT memo from Mark Miller, the USP is retroactive and should be added per a zero dollar change order to applicable current or future contracts that do not include the USP.

ICI WILL FOLLOW UP BY:

  • Reinforcing to ACEC
  • Pushing to get this revision into a RSP and into the 2018 S.S.